Certified Associate in Project Management (CAPM) — Question 312
How can a project manager represent a contingency reserve in the schedule?
Answer options
- A. Additional weeks of work to account for unknown-unknowns risks
- B. Task duration estimates of the best case scenarios
- C. Additional duration estimates in response to identified risks that have been accepted
- D. Milestones representing the completion of deliverables
Correct answer: C
Explanation
The correct answer is C because it directly pertains to adding time in the schedule for risks that have been acknowledged and accepted, which is the essence of a contingency reserve. Other options either misinterpret the concept of a contingency reserve or refer to unrelated elements in project management.