Certified Associate in Project Management (CAPM) — Question 305

Which of the following can a project manager use to represent defined team member roles in a group of tasks?

Answer options

Correct answer: B

Explanation

The Responsibility assignment matrix (RAM) is specifically designed to clarify the roles and responsibilities of team members in relation to tasks. The Work breakdown structure (WBS) focuses on breaking down project deliverables, while the Organizational breakdown structure (OBS) outlines the hierarchy within an organization. The Resource breakdown structure (RBS) categorizes resources but does not specify roles.