Certified Associate in Project Management (CAPM) — Question 303
Which tasks should a project manager accomplish in order to manage project scope correctly?
Answer options
- A. Define, Validate, and Control Scope; Control Schedule; Control Costs and Manage Stakeholder Engagement.
- B. Collect Requirements, Define Scope, Create WBS, Develop Schedule, and Manage Stakeholder Engagement.
- C. Plan Scope Management; Collect Requirements; Define, Validate, and Control Scope; and Create WBS.
- D. Define, Validate, and Control Scope; Control Costs; Manage Stakeholder Engagement; and keep budget under control.
Correct answer: C
Explanation
The correct answer is C because it includes all essential steps for managing project scope, such as planning scope management, collecting requirements, defining, validating, and controlling scope, and creating a work breakdown structure (WBS). Options A, B, and D include relevant tasks but omit critical components necessary for comprehensive scope management, thereby making them less effective.