Certified Associate in Project Management (CAPM) — Question 301
Which of the following conditions should the project manager consider when working on the scheduling for an adaptive environment?
Answer options
- A. Defining, sequencing, estimating activity durations, and developing a schedule model are so tightly linked that they are viewed as a single process.
- B. The detailed project schedule should remain flexible throughout the project to accommodate newly gained knowledge.
- C. An iterative scheduling and on-demand, pull-based scheduling will be required.
- D. To address the full delivery schedule, a range of techniques may be needed and then need to be adapted.
Correct answer: C
Explanation
Answer C is correct because iterative and pull-based scheduling allows for flexibility and responsiveness in adaptive environments. Options A and B, while relevant, do not directly address the need for iterative and on-demand approaches, and D, although mentioning adaptability, does not emphasize the scheduling aspect as clearly as C does.