Certified Associate in Project Management (CAPM) — Question 3

Which process is engaged when a project team member makes a change to project budget with the project manager's approval?

Answer options

Correct answer: D

Explanation

The correct answer is D, Control Costs, as this process involves monitoring and managing changes to the budget. The other options either refer to planning or estimating costs rather than the actual implementation and adjustment of the budget during the project.