Certified Associate in Project Management (CAPM) — Question 292

An agile team will begin to work on a project for a local conference. The team will deliver an information system with complete audience information, which includes many requirements. In order to begin working on the project, the team produces a checklist for a user-centric requirement that is needed to deliver the system.

Which checklist will the team produce?

Answer options

Correct answer: B

Explanation

The correct answer is B, Definition of ready (DoR), as it outlines the necessary criteria that must be met before work can commence on a user story. The other options represent different aspects of the agile process; the Definition of done (DoD) pertains to the completion of work, while product and sprint backlogs are collections of items that need to be worked on but do not specifically address readiness.