Certified Associate in Project Management (CAPM) — Question 290
A project manager was assigned to a project to implement a manufacturing system in a food factory. The main project objective is to deliver machines that are ready to process food. The project manager decides that this particular project does not require the use of timeboxed iterations.
Which method should the project manager adopt?
Answer options
- A. Scrum
- B. SAFe
- C. Feature-driven development (FDD)
- D. Kanban
Correct answer: D
Explanation
The correct answer is D, Kanban, as it focuses on continuous delivery without the need for timeboxed iterations, making it ideal for this scenario. Scrum, SAFe, and Feature-driven development (FDD) all rely on structured iterations, which the project manager has deemed unnecessary for this project.