Certified Associate in Project Management (CAPM) — Question 29

What process is included in Project Schedule Management?

Answer options

Correct answer: A

Explanation

The correct answer is A because estimating activity durations is a key component of Project Schedule Management, ensuring that timelines are realistic. Options B and D, while important to project management, pertain to planning and resource allocation rather than directly managing the schedule. Option C involves execution rather than the scheduling process.