Certified Associate in Project Management (CAPM) — Question 29
What process is included in Project Schedule Management?
Answer options
- A. Estimate Activity Durations
- B. Create Work Breakdown Structure (WBS)
- C. Direct and Manage Project Work
- D. Estimate Activity Resources
Correct answer: A
Explanation
The correct answer is A because estimating activity durations is a key component of Project Schedule Management, ensuring that timelines are realistic. Options B and D, while important to project management, pertain to planning and resource allocation rather than directly managing the schedule. Option C involves execution rather than the scheduling process.