Certified Associate in Project Management (CAPM) — Question 281
During the project planning process, which three of the following stakeholders are required to take part in the risk assessment meeting? (Choose three.)
Answer options
- A. Project team
- B. End user
- C. Project sponsor
- D. Subject matter experts (SMEs)
- E. Product owner
Correct answer: A, C, D
Explanation
The correct stakeholders for a risk assessment meeting include the Project team, Project sponsor, and Subject matter experts (SMEs) as they provide essential insights and oversight. The End user and Product owner, while important for other aspects of the project, do not typically contribute directly to the risk assessment process.