Certified Associate in Project Management (CAPM) — Question 265
During execution of a project, a team could not reach consensus on the decision-making approach. Which document should the team member refer to?
Answer options
- A. Project team charter
- B. Project management plan
- C. Project team assignments
- D. Project issue log
Correct answer: A
Explanation
The Project team charter outlines the roles, responsibilities, and decision-making processes within the team, making it the appropriate document to refer to in this situation. The Project management plan provides a broader overview of the project but does not specifically address decision-making. Project team assignments detail individual roles and responsibilities, while the Project issue log records problems but not the decision-making framework.