Certified Associate in Project Management (CAPM) — Question 258
A project team is changing its implementation method from a predictive to an adaptive approach to cope with the changing business needs. Which of the following plans will be significantly impacted?
Answer options
- A. Stakeholder engagement plan
- B. Quality management plan
- C. Configuration management plan
- D. Integration management plan
Correct answer: B
Explanation
The Quality management plan will be significantly impacted as an adaptive approach often requires adjustments in how quality is managed and assessed due to frequent changes. The other plans, while important, do not experience the same level of direct influence from changes in implementation methodology.