Certified Associate in Project Management (CAPM) — Question 252

In the last two iterations, a project team failed to deliver all of the stories on time. What should the project manager do first in order to prevent this from reoccurring?

Answer options

Correct answer: B

Explanation

The correct answer is B because identifying the root causes of delays is essential for implementing effective solutions. Options A and D do not address the underlying issues, and C does not provide proactive measures to prevent future delays.