Certified Associate in Project Management (CAPM) — Question 252
In the last two iterations, a project team failed to deliver all of the stories on time. What should the project manager do first in order to prevent this from reoccurring?
Answer options
- A. Extend the delivery time for the product since the management reserve allows it.
- B. Identify possible reasons for the delay and consult the risk register for corrective actions.
- C. Observe the project team's performance for the next two iterations before taking any action.
- D. Temporarily use another team for the next iteration and evaluate their performance.
Correct answer: B
Explanation
The correct answer is B because identifying the root causes of delays is essential for implementing effective solutions. Options A and D do not address the underlying issues, and C does not provide proactive measures to prevent future delays.