Certified Associate in Project Management (CAPM) — Question 250

An adaptive project manager is told that a new industry regulation will affect an upcoming deliverable. Where should this be recorded?

Answer options

Correct answer: B

Explanation

The correct answer is B, the Risk register, because this document is specifically designed to capture potential risks that could impact the project, including regulatory changes. The other options, such as User story and Sprint board, are more focused on project tasks and deliverables rather than documenting risks.