Certified Associate in Project Management (CAPM) — Question 248
Which of the following is provided by the critical path method?
Answer options
- A. Schedule float
- B. Total float
- C. Schedule value
- D. Earned value (EV)
Correct answer: B
Explanation
The correct answer is B, Total float, as the critical path method identifies the longest sequence of tasks and their float, which helps in understanding the flexibility of the schedule. Options A, C, and D do not directly relate to the critical path method's primary purpose, which is to manage and optimize project timelines.