A product owner and team members are working on tasks to be completed in the next project iteration. What should they do at this point in the project?
Answer options
- A. Follow the plan as initially designed by the team and stakeholders.
- B. Refine the task list, incorporating tasks not completed in previous iterations.
- C. Shorten the delivery time of the next iteration in order to increase the management reserve.
- D. Perform an iteration retrospective with the team.
Correct answer: B
Explanation
The correct answer is B because refining the task list allows the team to address unfinished work and ensure that all necessary tasks are prioritized for the next iteration. Answer A is incorrect as sticking to the original plan may not account for new tasks that need attention. Answer C is not advisable since shortening the delivery time could compromise quality. Answer D, while beneficial for team reflection, does not directly address the immediate task preparation needed for the upcoming iteration.