Certified Associate in Project Management (CAPM) — Question 236
Which project document is used to respond and provide information on threats and opportunities that may impact project execution?
Answer options
- A. Risk register
- B. Risk report
- C. Root cause analysis (RCA)
- D. Change log
Correct answer: A
Explanation
The Risk register is the appropriate document as it specifically tracks identified risks, including threats and opportunities, that could influence project execution. The Risk report provides summaries but does not detail actions for threats and opportunities. Root cause analysis (RCA) is focused on identifying the reasons for issues, while a Change log records changes made to the project but does not address risks directly.