Certified Associate in Project Management (CAPM) — Question 22
Which are inputs for the Plan Quality Management process?
Answer options
- A. Quality metrics, project documents, and financial performance
- B. Quality management plan, project documents, and quality metrics
- C. Project management plan, project documents, and organizational process assets
- D. Project management plan, quality metrics, and project documents
Correct answer: C
Explanation
The correct answer is C, as the inputs for the Plan Quality Management process include the Project management plan, project documents, and organizational process assets. Options A, B, and D include incorrect components that do not belong to the inputs required for this specific process.