Certified Associate in Project Management (CAPM) — Question 216
An obstacle has been identified and could potentially hinder the project’s progress. Where should this obstacle be documented?
Answer options
- A. Stakeholder register
- B. Communications management plan
- C. Assumption log
- D. Risk register
Correct answer: D
Explanation
The correct answer is the Risk register, as it is specifically designed to document potential obstacles that could impact a project's success. The Stakeholder register, Communications management plan, and Assumption log focus on different aspects of project management and do not serve the purpose of tracking risks.