Certified Associate in Project Management (CAPM) — Question 214
In an agile project, when should story prioritization be performed?
Answer options
- A. Within the first half of the project.
- B. Anytime during the project if the project manager allows it.
- C. Within the first half of the project, except for high-priority stories.
- D. Anytime during the project.
Correct answer: D
Explanation
The correct answer is D because story prioritization can be adjusted as needed throughout the agile project to respond to changing requirements or circumstances. Options A and C incorrectly limit prioritization to the early stages, and option B suggests a dependency on the project manager, which is not aligned with agile principles that encourage team flexibility.