Certified Associate in Project Management (CAPM) — Question 192
The project is in the execution phase and the project manager is expected to produce all required project artifacts. Which three are relevant artifacts produced during project execution? (Choose three.)
Answer options
- A. Work performance reports
- B. Issue log
- C. Business case
- D. Scope management plan
- E. Change requests
Correct answer: A, B, E
Explanation
Work performance reports, issue logs, and change requests are essential artifacts produced during project execution as they provide insights into project progress, track issues, and document changes. The business case and scope management plan are developed earlier in the project lifecycle and are not typically created during execution.