Certified Associate in Project Management (CAPM) — Question 192

The project is in the execution phase and the project manager is expected to produce all required project artifacts. Which three are relevant artifacts produced during project execution? (Choose three.)

Answer options

Correct answer: A, B, E

Explanation

Work performance reports, issue logs, and change requests are essential artifacts produced during project execution as they provide insights into project progress, track issues, and document changes. The business case and scope management plan are developed earlier in the project lifecycle and are not typically created during execution.