Certified Associate in Project Management (CAPM) — Question 175

A dynamic systems development method (DSDM) practitioner receives a new high-priority feature request. What should the practitioner do first?

Answer options

Correct answer: C

Explanation

The correct answer is C because prioritizing the new feature in the requirements list ensures that it is addressed in the next work period, aligning with DSDM's iterative approach. Options A and D are inappropriate as they could disrupt current priorities and workflows, while B may not be viable if the current work period's goals are not met.