Certified Associate in Project Management (CAPM) — Question 175
A dynamic systems development method (DSDM) practitioner receives a new high-priority feature request. What should the practitioner do first?
Answer options
- A. Develop the feature as a parallel work package.
- B. Shorten the current work period and begin the new work.
- C. Prioritize it in the requirements list for the next work period.
- D. Ask a dedicated team member complete it immediately.
Correct answer: C
Explanation
The correct answer is C because prioritizing the new feature in the requirements list ensures that it is addressed in the next work period, aligning with DSDM's iterative approach. Options A and D are inappropriate as they could disrupt current priorities and workflows, while B may not be viable if the current work period's goals are not met.