Certified Associate in Project Management (CAPM) — Question 149
In the project charter process, which three of the following are discussed during meetings held with stakeholders? (Choose three.)
Answer options
- A. Cost
- B. Project objectives
- C. Success criteria
- D. Phase transitions
- E. High-level deliverables
Correct answer: B, C, E
Explanation
The correct answers, B, C, and E, are essential components that define the project's focus, measures of success, and key outputs. Options A and D, while relevant to project management, are not typically the primary focus in initial stakeholder meetings related to the project charter.