Certified Associate in Project Management (CAPM) — Question 147
An organization's project management office (PMO) has issued guidelines that require a specific template to be used for onboarding resources for a project. Where can the project manager find this template?
Answer options
- A. Resources management plan
- B. Organizational systems access
- C. Organizational process assets
- D. Procurement management plan
Correct answer: C
Explanation
The correct answer is C, as the organizational process assets encompass templates, guidelines, and processes established by the PMO for project management. Options A and D refer to specific plans that may not contain the required onboarding template, while B pertains to access to systems rather than documentation.