Certified Associate in Project Management (CAPM) — Question 133
Which tool should a project manager use to calculate cost variance for a project?
Answer options
- A. Contingency analysis
- B. Expert judgment
- C. Actual cost
- D. Review lessons learned from similar projects
Correct answer: C
Explanation
The correct answer is C, as the Actual cost is necessary for calculating cost variance by comparing it to the planned budget. Options A and B do not provide the specific financial figures needed for this calculation, and D is useful for gaining insights but does not directly influence cost variance calculations.