In a demonstration meeting with a customer, the project team presented deliverables that were considered ready for customer use. The team based the results on a checklist of all the required criteria for the project.
Which of the following elements is the team using?
Answer options
- A. Definition of done (DoD)
- B. Burndown chart
- C. Definition of ready (DoR)
- D. Backlog refinement
Correct answer: A
Explanation
The project team is utilizing the Definition of Done (DoD) as it outlines the criteria that must be met for deliverables to be considered complete and ready for use. The Burndown chart is used for tracking progress, the Definition of Ready (DoR) pertains to the criteria for work items to be ready for the team to begin, and Backlog refinement involves the process of reviewing and prioritizing the backlog items.