Certified Associate in Project Management (CAPM) — Question 13
The project team is brainstorming on approaches to deliver the upcoming product launch for which the project has been chartered. The project manager is laying out hybrid, adaptive, iterative methods.
What is the team trying to address?
Answer options
- A. Co-location
- B. Life-cycle
- C. Diversity
- D. Management
Correct answer: B
Explanation
The team is primarily addressing the project life-cycle, which encompasses the various phases and methodologies involved in delivering the product. While co-location, diversity, and management are important aspects of project execution, the specific discussion around hybrid, adaptive, and iterative methods directly relates to the life-cycle of the project.