Certified Associate in Project Management (CAPM) — Question 127

A Scrumban team member wants to know what work has been completed this week. Which chart should the team member review?

Answer options

Correct answer: D

Explanation

The Burndown chart is specifically designed to show the amount of work completed over time, particularly in a sprint or iteration. The Gantt chart focuses on project timelines and dependencies, the Feature chart highlights features rather than completed work, and the Kanban chart visualizes work in progress rather than completed tasks.