Certified Associate in Project Management (CAPM) — Question 108
A project team member is reviewing the scope of a task with an end user and realizes that requirements have changed. Which project artifact should be used in this situation?
Answer options
- A. Scope management plan
- B. Risk management plan
- C. Configuration management plan
- D. Project management plan
Correct answer: D
Explanation
The correct answer is the Project management plan because it encompasses the overall project scope and adjustments due to changing requirements. The other options, while important, do not directly address the immediate need to manage and document changes in project scope.