Certified Pega Robotics System Architect v8.0 (2019) — Question 1

You are working on a team project with several other architects. Each architect is assigned to create activities for several applications. You are ready to add your
HR adapter project to the controller project.
Which three steps are required to add the HR project to the main solution? (Choose three.)

Answer options

Correct answer: A, B, E

Explanation

The correct steps to add the HR project involve creating an activity to log in, importing the project, and adding an assembly reference. Options C and D are not necessary for this specific integration process, as updating the .Net framework property is only needed if there is a version mismatch, and adding an existing project from the solution file is not required when using the import functionality.