Certified Pega System Architect v8.8 — Question 1
On a service level, the passed deadline interval is measured from ________________________.
Answer options
- A. the end of the goal interval
- B. the end of the deadline interval
- C. when a user begins the assignment
- D. when the assignment is ready for a user
Correct answer: A
Explanation