An engineer would like to change an incident's SLA according to the severity field changes.
How can the engineer achieve this task?

Answer options

Correct answer: A

Explanation

The correct answer is A, as a field trigger script can automatically execute actions when the severity field changes, allowing the SLA to be updated accordingly. Options B and C do not provide the automated capability needed for SLA adjustments, and D is impractical due to its reliance on manual intervention, which is inefficient.