Palo Alto Networks NGFW Engineer — Question 47
An administrator plans to upgrade a pair of active/passive firewalls to a new PAN-OS release. The environment is highly sensitive, and downtime must be minimized.
What is the recommended upgrade process for minimal disruption in this high availability (HA) scenario?
Answer options
- A. Suspend the active firewall to trigger a failover to the passive firewall. With traffic now running on the former passive unit, upgrade the suspended (now passive) firewall and confirm proper operation. Then fail traffic back and upgrade the remaining firewall.
- B. Shut down the currently active firewall and upgrade it offline, allowing the passive firewall to handle all traffic. Once the active firewall finishes upgrading, bring it back online and rejoin the HA cluster. Finally, upgrade the passive firewall while the newly upgraded unit remains active.
- C. Isolate both firewalls from the production environment and upgrade them in a separate, offline setup. Reconnect them only after validating the new software version, resuming HA functionality once both units are fully upgraded and tested.
- D. Push the new PAN-OS version simultaneously to both firewalls, having them upgrade and reboot in parallel. Rely on automated HA reconvergence to restore normal operations without manually failing over traffic.
Correct answer: A
Explanation
Option A is correct because it allows for a controlled failover, ensuring that traffic continues to flow while one firewall is upgraded. The other options introduce higher risks of downtime or complications, such as shutting down the active firewall (B), isolating both units (C), or attempting simultaneous upgrades (D), which could lead to network disruptions.