Oracle EPM Cloud Planning 2018 Implementation Essentials — Question 34
Which two items are NOT provided as configurable in Enterprise Planning and Budgeting Cloud (EPBCS)? (Choose two.)
Answer options
- A. Capital
- B. Public
- C. Financial Close
- D. Financials
- E. Strategic Modeling
Correct answer: A, E
Explanation
The correct answers are A and E because Capital and Strategic Modeling are not configurable within EPBCS. The other options, Public, Financial Close, and Financials, are available for configuration, allowing users to tailor their planning and budgeting processes.