Oracle Financial Reporting and Analysis Cloud 2017 Implementation Essentials — Question 7
Your customer complains that their project resources do not report their time promptly, which has resulted in incorrect reporting of project performance. What should you do to fix this problem? (Choose the best answer.)
Answer options
- A. Enable track missing time at project unit.
- B. Enable track missing time at project type.
- C. Enable track missing time at project template.
- D. Enable track missing time at business unit.
Correct answer: D
Explanation
Enabling track missing time at the business unit is the most effective solution because it encompasses all projects within that unit, ensuring timely reporting across the board. The other options are more limited in scope and may not address the issue effectively across all projects.