Oracle Financial Reporting and Analysis Cloud 2017 Implementation Essentials — Question 39
You have been asked to set up one active person, who is not a team member in the project, as a quality manager for each quality task created under projects.
However, when you try to assign the quality manager as Task Manager, you cannot find the person's name in the list of values. What is the reason for this problem? (Choose the best answer.)
Answer options
- A. The "Require Task Managers to be Project Team Members" profile option is set to No.
- B. The "Require Task Managers to be Project Team Members" profile option is set to Yes.
- C. The quality manager belongs to a department that is not associated with the project.
- D. The quality manager is not assigned with a supervisor.
Correct answer: A
Explanation
The correct answer is A because if the profile option is set to No, it allows individuals who are not project team members to be assigned as Task Managers. If it were set to Yes, the quality manager would need to be a member of the project team, which is not the case here. The other options suggest reasons that do not directly relate to the profile setting affecting Task Manager visibility.