Oracle Planning 2017 Implementation Essentials — Question 43

In what order should the import process be run when importing suppliers?

Answer options

Correct answer: B

Explanation

The correct sequence is B because it follows the hierarchical structure needed for proper associations between suppliers and their respective sites and contacts. The other options disrupt this order, which can lead to incomplete or incorrect data being imported.