Oracle Planning 2017 Implementation Essentials — Question 43
In what order should the import process be run when importing suppliers?
Answer options
- A. any order
- B. Supplier, Supplier Site, Supplier Site Contacts, Supplier Site Assignments
- C. Supplier, Supplier Site Contacts, Supplier Site, Supplier Site Assignment
- D. Supplier, Supplier Site Assignment, Supplier Site, Supplier Contacts
Correct answer: B
Explanation
The correct sequence is B because it follows the hierarchical structure needed for proper associations between suppliers and their respective sites and contacts. The other options disrupt this order, which can lead to incomplete or incorrect data being imported.