Oracle SOA Suite 12c Essentials — Question 50

Which expiration and escalation setting can be used to route a task a specified number of levels up a management chain if the assignee does not respond in a given time period?

Answer options

Correct answer: E

Explanation

The correct answer is 'E. Escalate after' because it specifically refers to the process of moving a task up the management chain when there is no response. The other options do not address the escalation of tasks; 'A' and 'B' refer to expiration without escalation, 'C' focuses only on routing to a manager, and 'D' pertains to renewing tasks, which does not involve escalation.