Oracle CPQ Cloud Service 2016 Implementation Specialist — Question 13

Your customer runs two daily shifts in her plant: Morning Shift and Evening Shift. A resource LATHE is assigned to the work center W1. There are five units of
LATHE available, of which three units are available for the Morning Shift and the remaining units are available for the Evening Shits.
Which two actions must you perform to associate LATHE with W1?

Answer options

Correct answer: B, E

Explanation

The correct actions to associate LATHE with W1 are to not check the Available 24 Hours box and enter 3 units for the Morning Shift, as this accurately reflects resource availability. Option E is also correct as it provides a percentage representation of the units available in the Morning Shift, which aligns with the resource assignment. The other options either incorrectly check the 24 Hours box or misrepresent the resource availability in the shifts.