Oracle Field Service Cloud Service 2016 Implementation Specialist — Question 34
Which process requires the Release Planning recommendation process to be executed manually so that a supply order gets created?
Answer options
- A. Manual orders using File Based Data Load
- B. Min-Max planning replenishing a transfer order
- C. Back-to-Back Order
- D. Drop Ship Order
- E. Min-Max planning replenishing a purchase request
Correct answer: C
Explanation
The Back-to-Back Order process is unique in that it requires the Release Planning recommendation to be executed manually to create a supply order. The other options either automate the process or do not necessitate manual intervention for order creation.