Oracle Field Service Cloud Service 2016 Implementation Specialist — Question 31
The orchestration process fulfillment task is performed by an external system and you need to register the connector to integrate the non-Fusion system.
Which two steps would you perform to invoke the external connector service endpoint URL? (Choose two.)
Answer options
- A. Create a new web service connector to register the endpoint URL.
- B. Create a new fulfilment task service to register the endpoint URL.
- C. Create a new routing rule for the fulfilment task to call the endpoint URL.
- D. Create a new routing rule for the fulfilment task to call the connector.
Correct answer: A, D
Explanation
The correct actions are to create a new web service connector and a routing rule for the fulfillment task to call the connector. Option B is incorrect because creating a new fulfillment task service does not directly register the endpoint URL. Option C is also incorrect as it suggests calling the endpoint URL directly rather than the connector, which is necessary for integration.