Oracle WebLogic Server 12c: Advanced Administration II — Question 21
Which two automatic migration scenarios require node manager for all migratable services? (Choose two.)
Answer options
- A. Consensus leasing
- B. Database leasing with no pre and post migration scripts
- C. Database leasing with pre and post migration scripts
- D. Synchronous leasing
Correct answer: A, C
Explanation
The correct answers are A and C because both Consensus leasing and Database leasing with pre and post migration scripts require node manager for the management of the migratable services during the migration process. Options B and D do not require node manager, making them incorrect for this scenario.