Oracle Analytics Cloud 2020 Implementation Essentials — Question 14
You have added a new task to a close schedule with a task due date past the defined end date of the schedule. What is the result of the change?
Answer options
- A. An error, you cannot add a new task past the due date.
- B. The task will not run.
- C. The new task will run outside of the schedule end date.
- D. The schedule end date changes to match the end date of the task.
Correct answer: D
Explanation
The correct answer is D because when a new task with a due date beyond the schedule's end date is added, the schedule's end date is updated to accommodate the new task. Options A and B are incorrect as no error occurs, and the task will be executed. Option C is misleading because the schedule's end date will change, rather than the task running outside of it.