Oracle Talent Management Cloud 2022 Implementation Essentials — Question 3

Your company uses an accounting calendar with periods that are identical to calendar months. A contract resource has been identified to work for six months on an accounting close cycle project. The resource is planned to start with 10 days left in the first period and to end 20 days into the last period. For the remaining periods, the resource must be loaded on all working days of the month. You are required to distribute the budget, forecast, and planning amounts across periods based on the task duration.
Which predefined spread curve must be used to meet this requirement?

Answer options

Correct answer: A

Explanation

The Even spread curve is appropriate here because it distributes the budget equally across all months, which aligns with the requirement of scheduling the resource for all working days in the remaining periods. The Daily Spread Basis would not apply since it focuses on daily distribution rather than equal monthly allocation. The S-Curve, Bell Curve, and Back Loaded options are not suitable as they represent varying distribution methods that do not match the need for uniformity in this scenario.