Oracle Talent Management Cloud 2022 Implementation Essentials — Question 14
Shift is one of the key elements in defining project and resource calendars.
Which two additional key elements are required to define the project and resource calendars? (Choose two.)
Answer options
- A. Schedule Exceptions
- B. Workday Patterns
- C. Time off
- D. Expenditure Type
- E. Accounting Calendar
Correct answer: A, D
Explanation
The correct answers, Schedule Exceptions and Expenditure Type, are necessary for accurately defining project and resource calendars as they address specific scheduling needs and financial tracking. Workday Patterns and Time off, while important, do not provide the same level of detail needed for calendar definitions, and Accounting Calendar is not directly related to project scheduling.