Nokia Certified Network Professional – IP/MPLS Services — Question 15
How is it possible to check the activation status of GMRE on a node?
Answer options
- A. The GMRE reachability can be tested via ping request from NFM-T
- B. The ControlPlane status column on the node list displays the GMRE status for the selected node
- C. The GMRE activation status is reported in the supervision state column on the node list
- D. The GMRE activation status is reflected on the color of the icon representing the node
Correct answer: D
Explanation
The correct answer, D, indicates that the node's icon color indicates the GMRE activation status, providing a quick visual reference. Options A, B, and C describe methods that do not directly reflect the activation status, making them less suitable for this specific check.