NetApp Certified Implementation Engineer – NVMe — Question 75
Your customer has a defective FAS8300 controller serving FC LUNs.
In this scenario, which step is required after replacing the controller?
Answer options
- A. Call support to update the new node system ID.
- B. Update the WWPNs on the FC LIFs.
- C. Call support to update the new node's serial number.
- D. Update the node licenses.
Correct answer: B
Explanation
The correct action is to update the WWPNs on the FC LIFs because the new controller will have different WWPNs that need to be configured for proper connectivity. The other options, while they might seem relevant, do not directly address the immediate requirement of ensuring the new controller can communicate effectively with the existing FC infrastructure.