NetApp Certified Implementation Engineer – NVMe — Question 23

You are preparing to install a new 2-node AFF A250 system at a customer site with an existing cluster that uses NetApp CN1610 cluster interconnect switches.
In this scenario, what are two valid actions for this installation? (Choose two.)

Answer options

Correct answer: C, D

Explanation

The correct answers are C and D. Creating a new switchless cluster aligns with the requirements for the installation, as it does not depend on the existing switches. Migrating to new switches and adding the new nodes also ensures compatibility. Options A and B are incorrect because they imply using the existing CN1610 switches, which may not be suitable for the new installation scenario.