NetApp Certified Implementation Engineer – NVMe — Question 14

You are preparing to physically install a new AFF A400 cluster into a customer’s racks. All equipment has been delivered to the customer’s site.
Which three tools do you need to complete this installation? (Choose three.)

Answer options

Correct answer: A, B, C

Explanation

The correct tools for the installation of the AFF A400 cluster include additional network cables for connectivity, a Phillips #2 screwdriver for securing components, and a laptop computer for configuration and management. The slide rail kit and cable management tray are not essential for the physical installation process.