NetApp Certified Implementation Engineer – Data Protection — Question 57
Your company has recently decided to stop using the Fibre Channel Protocol (FCP) in the data center. You are asked to decommission FCP and reuse any UTA2 ports to 10 GbE.
Which two steps are involved in this task? (Choose two.)
Answer options
- A. Reboot the nodes.
- B. Destroy any FC LIFs hosted on UTA2 ports.
- C. Remove the FCP license from all nodes in the cluster.
- D. License additional phttps://www.netapp.com/pdf.html?item=/media/13482-tr4375pdf.pdforts for 10 GbE connectivity.
Correct answer: A, C
Explanation
The correct actions are to reboot the nodes to ensure that all changes take effect and to remove the FCP license from all nodes in the cluster, as this is necessary for decommissioning FCP. The other options, such as destroying FC LIFs or licensing additional ports, are not required steps in this process.