Certified Professional Contracts Manager (CPCM) — Question 1
At which level of CMM model, basic contract management processes are integrated with other organizational core processes such as cost control, schedule and performance management and system engineering?
Answer options
- A. Ad hoc
- B. managed
- C. mature
- D. structured
Correct answer: B
Explanation
The correct answer is B, as the 'managed' level of the CMM model indicates that processes are defined and integrated with other core functions. The 'Ad hoc' level lacks structured processes, while 'mature' and 'structured' imply higher levels of development, which do not specifically address the integration of basic contract management processes.